The Landscape Plan
The Picacho Hills Landscape Plan project was created to focus on common areas
not maintained or improved by active HOA's in Picacho Hills.
- The first phase of the project in 2017 was the corner of Picacho Hills Drive and Fairway Village Drive.
- The other corner of Fairway Village Drive and Picacho Hills Drive was landscaped in Spring, 2018.
- In the summer of 2018, the next phase included Picacho Hills Drive at lower Mira Montes.
- Shortly thereafter, landscaping began along Barcelona Ridge Road down the hill from upper Mira Montes.
- Since then, areas along Barcelona Ridge and the south border of Picacho Hills Drive have been improved.
- In 2024, the area from the Casitas to Via Norte was graveled and planted.
Landscaping: A Journey of Progress and Community Engagement




We extend our gratitude to everyone who has previously supported the Picacho Hills Property Owners Association Landscape Fund. This project is a continuous endeavor, involving new enhancements and the upkeep of existing features.
To contribute to the Association Landscape Fund, send a check to:
Picacho Hills Property Owners Association
Box 51
Fairacres NM 88033